Back from the sunny Med. Where to begin? There is all kinds of stuff, but K at BJ had a really good post on local municipal utilities, even in conservative areas, breaking away from the nationalized ALEC propaganda about alternative energy, doing their own thing, saving money and generally moving ahead smartly:
Just 10 weeks after breaking ground, construction of Bryan Municipal Utilities’ solar generation project has been completed, and power is being supplied to Bryan’s electrical grid.
BMU broke ground for the $7.42 million solar array in early December 2011. By mid-January 2012, all 23,530 solar modules were in place, and by the first week of February, the solar plant was fully operational.
“The solar arrays are producing just as expected, and we have seen them perform up to the maximum capacity of 1.8 megawatts on sunny days,” said Steve Casebere, director of utilities.
As of February 13, the solar field has produced 100 MWh, which means it has also produced 100 solar renewable energy credits. BMU sold 2,500 solar RECs produced in 2012 to American Electric Power and Duke Energy for $606,500.
In addition to the power and energy credits, what the solar plant does not produce is valuable. With the energy produced to date, the solar field has saved 76 tons of carbon dioxide and 3.6 tons of methane gas emissions.